Blog article hero imageBlog article hero image

Over 1,000 km of power line corridors have been cleared and more than 23,000 hazardous trees have been removed

ERP North has completed a comprehensive set of activities to prepare the power distribution network across its entire licensed territory for the upcoming 2026–2027 winter season. These measures are aimed at increasing power supply reliability, mitigating the risk of outages, and ensuring a rapid response to adverse weather conditions.

One of the primary network maintenance activities is clearing corridors along overhead power lines. To date, over 1,000 km of corridors along the medium-voltage distribution network have been cleared. Additionally, more than 23,000 trees outside the power line easements, which posed a potential risk to the security of the facilities and the continuity of the power supply, have been removed.

Efforts to secure the power distribution infrastructure are also ongoing. This year, bird protection devices were installed on over 3,000 medium-voltage poles as part of the "Safe Sky for Birds in Northeast Bulgaria" project under the LIFE program, aimed at reducing the risk of electrocution for birds and improving the safety of the distribution network.

As part of the winter season preparations, repairs, maintenance, and the replacement of worn-out components of the distribution infrastructure have been carried out. 385 km of low-voltage networks have been reconstructed, 8,758 medium-voltage insulators have been replaced, and 2,286 new poles have been installed. Furthermore, 11 km of medium-voltage cables and 76 km of low-voltage cables have been laid.

Significant projects completed include the construction of a 2.8 km long 110 kV cable line between the Ruse and Ruse-North substations with an investment of 1.252 million euros, and the commissioning of a new power transformer at the Maksuda substation in Varna for over 1.5 million euros, which increased the substation's installed capacity from 75 to 125 MVA.

The implementation of modern technologies for remote network management is of particular importance for power supply security. In 2026, 44 new remotely controlled devices were installed. These allow for faster localization and isolation of faults, as well as more efficient management of the power distribution network.

To respond to emergency situations, ERP North has 378 repair teams distributed across the nine administrative regions. Round-the-clock readiness is ensured through a shift system, with 68 teams available at any given time outside of working hours. If necessary, teams and equipment can be redeployed to the most affected areas. They have access to 421 all-terrain vehicles and 146 specialized vehicles, including all-terrain aerial platforms, mobile cranes, and other types of specialized equipment.

To ensure power supply during major outages, ERP North has 10 mobile diesel generators with a total capacity of 3,845 kVA, three portable generators with a capacity of 30 kVA each, and a mobile transformer substation with a capacity of 1,000 kVA.