EP North invests BGN 1.36 million in cable line in central Ruse
Posted on
29.12.2021
Author
ENERGO-PRO
Time to read

Elektrodistribuenie Sever AD replaced a 110 kV cable line between Ruse-Center and Leventa substations in the city of Ruse. The investment amounts to BGN 1.36 million. The oil cable used so far has been replaced with a new one — with insulation of chemically cross-linked polyethylene with a length of more than 2000 m, which will guarantee a high degree of security in the electricity supply to consumers.
The facility will provide more reliable and secure power supply to over 32,500 subscribers in the central part of the city. Ruse.
Construction and installation works on the route of the cable line were carried out with the assistance of the Municipality of Ruse.